Work begins on second emptying machine at Sellafield waste silo

SHARE:

Work has begun to install the second of three emptying machines at Sellafield’s Magnox Swarf Storage Silo. The first piece of the 350-tonne machine – a transfer tunnel – was lifted into the building last month.


The silo contains an estimated 60,000 items of intermediate level nuclear waste in 22 chambers. It was built in the 1960s without a plan for how it would be emptied.

Engineers have been working for decades to design, build, and install three machines to do the job. One is fully built, the second is now under construction, and a third will follow.

Waste retrievals are scheduled to start later this year. By 2024, all three machines should be up and running. Retrievals are set to be completed by 2045. Decommissioning the building is one of the Nuclear Decommissioning Authority’s priority programmes.

Chris Halliwell, head of the Magnox Swarf Storage Silo for Sellafield Ltd, said:

"This is another milestone on the journey to tackling our biggest challenge.

"It’s a statement of our intent to press on with the job as quickly and safely as we can."

The machines will move over the top of the building’s 16-metre deep chambers on rails. Once in place over a chamber, it will lock on and tooling will reach in to pull up the waste inside. The material will be placed in boxes and dispatched out of the building via the transfer tunnel.

The boxes will then be transferred to a new modern storage building on the Sellafield site. The exact contents of the silo are unknown because record keeping at the time was patchy. The bulk of its inventory is radioactive scrap metal and contaminated engineering debris.

COMMENTS

$show=404

[/fa-rss/ LATEST STORIES FROM LITTLE IRELAND]_$type=three$author=hide$cm=0$ct=0$va=0$hide=home

$show=post

[/fa-arrow-alt-circle-down/ READ ALL ABOUT IT:]_$type=one$m=0$c=1$cm=0$l=0$va=0$hide=home$sr=random

$type=three$m=0$l=0$c=6$cm=0$hide=home$source=random

$show=post

Name

Book,1,Cleator Moor History,44,Cleator Moor News,129,Copeland Borough Council,96,Cumbria News,1696,News,2482,Photography,23,Photos For Sale,9,Photos Of Cleator Moor,9,Photos of Cumbria,14,UK News,286,Walking Routes,3,West Cumbria News,387,Your MP,54,
ltr
item
Cleator Moor | Cumbria: Little Ireland: Work begins on second emptying machine at Sellafield waste silo
Work begins on second emptying machine at Sellafield waste silo
https://i.ytimg.com/vi/6XSKtsRFPXY/hqdefault.jpg
https://i.ytimg.com/vi/6XSKtsRFPXY/default.jpg
Cleator Moor | Cumbria: Little Ireland
https://www.littleireland.co.uk/2020/01/work-begins-on-second-emptying-machine.html
https://www.littleireland.co.uk/
https://www.littleireland.co.uk/
https://www.littleireland.co.uk/2020/01/work-begins-on-second-emptying-machine.html
true
4367044361856627147
UTF-8
Loaded All Posts Not found any posts VIEW ALL Readmore Reply Cancel reply Delete By Home PAGES POSTS View All SUGGESTED READING LITTLE IRELAND ARCHIVE SEARCH ALL POSTS Not found any post match with your request Back Home Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sun Mon Tue Wed Thu Fri Sat January February March April May June July August September October November December Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec just now 1 minute ago $$1$$ minutes ago 1 hour ago $$1$$ hours ago Yesterday $$1$$ days ago $$1$$ weeks ago more than 5 weeks ago Followers Follow THIS PREMIUM CONTENT IS LOCKED STEP 1: Share to a social network STEP 2: Click the link on your social network Copy All Code Select All Code All codes were copied to your clipboard Can not copy the codes / texts, please press [CTRL]+[C] (or CMD+C with Mac) to copy Table of Content